Williams Company off and running with Maynard Evans High School construction

02/04/10

July 26th, 2010 - As of July 23rd, Williams Company Building Division, Inc. is off and running at the Evans High School project. The demolition was completed in January and all the underground work finished up at the beginning of the summer. With a long way to go to the November 2011 completion date, the excitement is still evident at the jobsite now that there are some building pads in place. Keep checking in to see our progress and check out the photos below.

May 10, 2010 - Williams Company Building Division, Inc. started on the Underground Storm system at Evans High School. The demolition of the outparcels is also underway, as well as importing nearly 50,000 cubic yards to raise up the building pad to 114.5'. The next milestone item for the High School is the Chilled Water Loop, which is set to start on 5/25/10.

January 25, 2010 - Williams Company Building Division, Inc. completed demolition of all Evans High School (located at 4949 Silver Star Road, Orlando, FL 32808) buildings with only the front office building left. Approximately 30,000 tons of debris were removed from the site in only 43 days, from top down through foundations.

 

Back to Press Releases